This log records every data update behind the site so a figure can always be traced to a release. Wage percentiles come from the annual BLS OEWS release and change once a year; construction employment is refreshed monthly; county contractor pay quarterly; and Davis-Bacon wage determinations are re-read every week after the Department of Labor publishes its Thursday modifications. Each Davis-Bacon change is listed below with the determination number, the classification affected and the old and new base + fringe, so contractors can see exactly what moved and when.
Data releases and Davis-Bacon modifications picked up by the weekly refresh. OEWS wages: May 2025 release. Prevailing wage index as of 2026-11-06. Construction employment through 2026-09.
| Date | State | Determination | Type | Classification | Was (base + fringe) | Now |
|---|---|---|---|---|---|---|
| 2026-11-06 | CO | CO20260001 | Building | ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING AND INSTALLATION O | $46.80 + $19.53 | $49.35 + $19.93 |
| 2026-11-06 | CO | CO20260001 | Building | ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING AND INSTALLATION O | $36.95 + $14.41 | $38.45 + $15.10 |
| 2026-11-06 | CO | CO20260001 | Building | ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING AND INSTALLATION O | $40.70 + $18.47 | $43.20 + $18.55 |
| 2026-11-06 | MS | MS20260050 | Building | PLUMBER (INCLUDES HVAC PIPE INSTALLATION (EXCLUDES HVAC UNIT | $29.91 + $11.97 | $33.08 + $13.10 |
| 2026-11-06 | MS | MS20260050 | Building | PIPEFITTER (INCLUDES HVAC UNIT INSTALLATION (EXCLUDES HVAC P | $30.41 + $11.47 | $33.08 + $13.10 |
| 2026-11-06 | MS | MS20260052 | Building | PLUMBER (INCLUDES HVAC PIPE INSTALLATION (EXCLUDES HVAC UNIT | $29.91 + $11.97 | $33.08 + $13.10 |
| 2026-11-06 | MS | MS20260052 | Building | PIPEFITTER (INCLUDES HVAC UNIT INSTALLATION (EXCLUDES HVAC P | $30.41 + $11.47 | $33.08 + $13.10 |
| 2026-11-06 | NV | NV20260060 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260060 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260060 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260060 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260060 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260061 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260061 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260061 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260061 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260061 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260062 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260062 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260062 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260062 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260062 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260063 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260063 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260063 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260063 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260063 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260064 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260064 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260064 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260064 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260064 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260065 | Heavy | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260065 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260065 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260065 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260065 | Heavy | Elevator Constructor: Journeyman Mech | $69.43 + $40.04 | $72.36 + $46.67 |
| 2026-11-06 | NV | NV20260066 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260066 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260066 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260066 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260066 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260067 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260067 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260067 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260067 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260067 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260068 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260068 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260068 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260068 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260068 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260069 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260069 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260069 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260069 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260069 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260070 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260070 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260070 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260070 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260070 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260071 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260071 | Heavy | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260071 | Heavy | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260071 | Heavy | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260071 | Heavy | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260072 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260072 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260072 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260072 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260072 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260073 | Heavy | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260073 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260073 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260073 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equi | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260073 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Grou | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260074 | Heavy | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260074 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260074 | Heavy | Electrician-Communication Technician: Communication-Installe | $40.94 + $21.56 | $42.34 + $23.70 |
| 2026-11-06 | NV | NV20260074 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260074 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260075 | Heavy | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260075 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260075 | Heavy | Electrician-Communication Technician: Communication-Installe | $40.94 + $21.56 | $42.34 + $23.70 |
| 2026-11-06 | NV | NV20260075 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260075 | Heavy | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260076 | Heavy | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260076 | Heavy | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260076 | Heavy | Electrician-Lineman: Equipment Specialist | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260076 | Heavy | Electrician-Lineman: Groundman | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260076 | Heavy | Electrician-Lineman: Lineman | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-11-06 | NV | NV20260077 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260077 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260077 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260077 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260077 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260078 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260078 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260078 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260078 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260078 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260079 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260079 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260079 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260079 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260079 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260080 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260080 | Building | Alarm Installer: Journeyman | $81.87 + $0.00 | $84.49 + $0.00 |
| 2026-11-06 | NV | NV20260080 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260080 | Building | Bricklayer: Journeyman | $56.66 + $21.81 | $56.66 + $21.82 |
| 2026-11-06 | NV | NV20260080 | Building | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260081 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260081 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260081 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260081 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260081 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260082 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260082 | Building | Alarm Installer: Journeyman | $81.87 + $0.00 | $84.49 + $0.00 |
| 2026-11-06 | NV | NV20260082 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260082 | Building | Bricklayer: Journeyman | $53.57 + $21.26 | $56.66 + $21.82 |
| 2026-11-06 | NV | NV20260082 | Building | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260083 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260083 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260083 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260083 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260083 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260084 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260084 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260084 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260084 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260084 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260085 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260085 | Building | Alarm Installer: Journeyman | $81.87 + $0.00 | $84.49 + $0.00 |
| 2026-11-06 | NV | NV20260085 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260085 | Building | Bricklayer: Journeyman | $53.57 + $21.26 | $56.66 + $21.82 |
| 2026-11-06 | NV | NV20260085 | Building | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260086 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260086 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260086 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260086 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260086 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260087 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260087 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260087 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260087 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260087 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260088 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260088 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260088 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260088 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260088 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260089 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260089 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260089 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260089 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260089 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260090 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260090 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260090 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260090 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260090 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260091 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260091 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260091 | Building | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260091 | Building | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260091 | Building | Floorcoverer: Journeyman | $47.82 + $20.55 | $48.92 + $21.05 |
| 2026-11-06 | NV | NV20260092 | Building | Air Balance Technician: Journeyman | $59.85 + $33.51 | $62.09 + $34.28 |
| 2026-11-06 | NV | NV20260092 | Building | Alarm Installer: Journeyman | $41.41 + $0.00 | $42.74 + $0.00 |
| 2026-11-06 | NV | NV20260092 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260092 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260092 | Building | Electrician-Communication Technician: Installer | $38.90 + $16.61 | $42.40 + $17.48 |
| 2026-11-06 | NV | NV20260093 | Building | Alarm Installer: Journeyman | $42.08 + $0.00 | $43.43 + $0.00 |
| 2026-11-06 | NV | NV20260093 | Building | Boilermaker: Journeyman | $76.62 + $0.00 | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260093 | Building | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260093 | Building | Electrician-Communication Technician: Communication Technici | $50.93 + $0.00 | $52.56 + $0.00 |
| 2026-11-06 | NV | NV20260093 | Building | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equi | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260094 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260094 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260094 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260094 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260094 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260095 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260095 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260095 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260095 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260095 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260096 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260096 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260096 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260096 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260096 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260097 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260097 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260097 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260097 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260097 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260098 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260098 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260098 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260098 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260098 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260099 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260099 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260099 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260099 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260099 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260100 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260100 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260100 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260100 | Highway | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260100 | Highway | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260101 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260101 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260101 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260101 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260101 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260102 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260102 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260102 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260102 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260102 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260103 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260103 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260103 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260103 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260103 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260104 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260104 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260104 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260104 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260104 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260105 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260105 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260105 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260105 | Highway | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260105 | Highway | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260106 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260106 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heav | $47.60 + $20.73 | $49.98 + $20.92 |
| 2026-11-06 | NV | NV20260106 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $61.67 + $22.65 | $64.75 + $23.74 |
| 2026-11-06 | NV | NV20260106 | Highway | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260106 | Highway | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260107 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260107 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260107 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260107 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260107 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260108 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260108 | Highway | Fence Erector: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260108 | Highway | Flagperson: Journeyman | $37.03 + $33.59 | $39.53 + $34.24 |
| 2026-11-06 | NV | NV20260108 | Highway | Highway Stripers: Journeyman | $38.53 + $33.59 | $41.03 + $34.24 |
| 2026-11-06 | NV | NV20260108 | Highway | Hod Carrier-Brick Mason Tender: Journeyman | $38.84 + $33.59 | $41.34 + $34.24 |
| 2026-11-06 | NV | NV20260109 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + — |
| 2026-11-06 | NV | NV20260109 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260109 | Highway | Electrician-Neon Sign: Journeyman | $63.15 + — | $65.17 + $0.00 |
| 2026-11-06 | NV | NV20260109 | Highway | Electrician-Wireman: Cable Splicer | $55.78 + $30.66 | $59.80 + $31.81 |
| 2026-11-06 | NV | NV20260109 | Highway | Electrician-Wireman: Wireman | $48.50 + $29.99 | $52.00 + $31.81 |
| 2026-11-06 | NV | NV20260110 | Highway | Boilermaker: Journeyman | $76.62 + — | $79.07 + $0.00 |
| 2026-11-06 | NV | NV20260110 | Highway | Cement Mason: Journeyman | $43.06 + $13.86 | $46.47 + $14.45 |
| 2026-11-06 | NV | NV20260110 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equi | $54.50 + $22.88 | $55.59 + $23.04 |
| 2026-11-06 | NV | NV20260110 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Grou | $41.68 + $22.23 | $42.51 + $22.37 |
| 2026-11-06 | NV | NV20260110 | Highway | Electrician-Lineman/Groundman/Heavy Equipment Operator: Line | $72.26 + $26.05 | $74.43 + $26.76 |
| 2026-10-30 | IA | IA20260001 | Heavy | CEMENT MASON/CONCRETE FINISHER (SCOTT COUNTY) | $33.12 + $28.39 | $34.62 + $28.94 |
| 2026-10-30 | IA | IA20260073 | Building | CEMENT MASON/CONCRETE FINISHER | $32.29 + $28.45 | $33.21 + $29.43 |
| 2026-10-30 | IA | IA20260073 | Building | PLASTERER | $32.29 + $28.45 | $39.12 + $23.15 |
| 2026-10-30 | IL | IL20260012 | Heavy | CEMENT MASON/CONCRETE FINISHER (ROCK ISLAND COUNTY) | $28.52 + $24.04 | $34.62 + $28.94 |
| 2026-10-23 | AK | AK20260001 | Building | POWER EQUIPMENT OPERATOR (GROUP 1) ASPHALT ROLLER: BREAKDOWN | $53.23 + $29.50 | $55.75 + $30.60 |
| 2026-10-23 | AK | AK20260003 | Residential | POWER EQUIPMENT OPERATOR: (1) BACKHOE: 3 YARDS AND UNDER | $53.23 + $29.50 | $55.75 + $30.60 |
| 2026-10-23 | AK | AK20260003 | Residential | POWER EQUIPMENT OPERATOR: (1) BULLDOZER | $53.23 + $29.50 | $55.75 + $30.60 |
| 2026-10-23 | AK | AK20260003 | Residential | POWER EQUIPMENT OPERATOR: (1) MOTOR PATROL GRADERS | $53.23 + $29.50 | $55.75 + $30.60 |
| 2026-10-23 | AK | AK20260003 | Residential | POWER EQUIPMENT OPERATOR: (1A) BACKHOE: OVER 3 YARDS | $55.33 + $29.50 | $57.95 + $30.60 |
| 2026-10-23 | AK | AK20260003 | Residential | POWER EQUIPMENT OPERATOR: (3) ROLLERS: OTHER THAN PLANTMIX | $51.46 + $29.50 | $53.90 + $30.60 |
| 2026-10-23 | AK | AK20260005 | Residential | POWER EQUIPMENT OPERATOR (GROUP 1) ASPHALT ROLLER: BREAKDOWN | $53.23 + $29.50 | $55.75 + $30.60 |
| 2026-10-23 | CA | CA20260014 | Building | BRICKLAYER; MARBLE SETTER | $45.53 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | CA | CA20260014 | Building | MARBLE FINISHER | $43.38 + $15.36 | $46.97 + $17.17 |
| 2026-10-23 | CA | CA20260014 | Building | TILE FINISHER | $37.96 + $13.77 | $41.55 + $15.65 |
| 2026-10-23 | CA | CA20260014 | Building | TERRAZZO FINISHER | $42.11 + $14.67 | $46.09 + $15.71 |
| 2026-10-23 | CA | CA20260014 | Building | TERRAZZO WORKER/SETTER | $49.62 + $15.26 | $54.13 + $16.01 |
| 2026-10-23 | CA | CA20260017 | Residential | BRICKLAYER; MARBLE SETTER (LOS ANGELES COUNTY) | $50.07 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | CA | CA20260017 | Residential | BRICKLAYER; MARBLE SETTER (ORANGE COUNTY) | $50.07 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | CA | CA20260017 | Residential | BRICKLAYER; MARBLE SETTER (RIVERSIDE & SAN BERNARDINO CO | $50.07 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | CA | CA20260017 | Residential | BRICKLAYER; MARBLE SETTER (VENTURA COUNTY) | $50.07 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | CA | CA20260017 | Residential | BRICKLAYER; MARBLE SETTER (SAN LUIS OBISPO AND SANTA BARBARA | $50.07 + $20.29 | $50.32 + $21.23 |
| 2026-10-23 | HI | HI20260001 | Building | ROOFERS (INCLUDING BUILT UP, COMPOSITION AND SINGLE PLY) | $43.15 + $21.21 | $45.55 + $23.36 |
| 2026-10-23 | IL | IL20260001 | Building | CEMENT MASON/CONCRETE FINISHER (HENDERSON (NORTHERN HALF), M | $28.16 + $23.48 | $33.21 + $29.43 |
| 2026-10-23 | IL | IL20260008 | Building | OPERATOR: POWER EQUIPMENT, GROUP 4 (BUILDING AND RESIDENTIAL | $59.20 + $51.00 | $63.20 + $53.05 |
| 2026-10-23 | IL | IL20260008 | Building | OPERATOR: POWER EQUIPMENT, GROUP 3 (BUILDING AND RESIDENTIAL | $60.95 + $51.00 | $64.95 + $53.05 |
| 2026-10-23 | IL | IL20260008 | Building | OPERATOR: POWER EQUIPMENT, GROUP 2 (BUILDING AND RESIDENTIAL | $63.50 + $51.00 | $67.50 + $53.05 |
| 2026-10-23 | IL | IL20260008 | Building | OPERATOR: POWER EQUIPMENT, GROUP 1 (BUILDING AND RESIDENTIAL | $64.80 + $51.00 | $68.80 + $53.05 |
| 2026-10-23 | IL | IL20260009 | Building | OPERATOR: POWER EQUIPMENT, GROUP 4 (BUILDING AND RESIDENTIAL | $59.20 + $51.00 | $63.20 + $53.05 |
| 2026-10-23 | IL | IL20260009 | Building | OPERATOR: POWER EQUIPMENT, GROUP 3 (BUILDING AND RESIDENTIAL | $60.95 + $51.00 | $64.95 + $53.05 |
| 2026-10-23 | IL | IL20260009 | Building | OPERATOR: POWER EQUIPMENT, GROUP 2 (BUILDING AND RESIDENTIAL | $63.50 + $51.00 | $67.50 + $53.05 |
| 2026-10-23 | IL | IL20260009 | Building | OPERATOR: POWER EQUIPMENT, GROUP 1 (BUILDING AND RESIDENTIAL | $64.80 + $51.00 | $68.80 + $53.05 |
| 2026-10-23 | PA | PA20260063 | Building | ELECTRICIAN (ALARM INSTALLATION, INSTALLATION OF SOUND AND C | $39.27 + $22.28 | $48.02 + $29.04 |
| 2026-10-23 | SC | SC20260034 | Highway | CARPENTER, FORM WORK ONLY (BERKELEY, DORCHESTER) | $13.50 + $0.00 | $19.96 + $0.00 |
| 2026-10-23 | SC | SC20260034 | Highway | CARPENTER, FORM WORK ONLY (CHARLESTON) | $13.07 + $0.00 | $19.32 + $0.00 |
| 2026-10-23 | SC | SC20260034 | Highway | CARPENTER, FORM WORK ONLY (HORRY) | $14.29 + $0.00 | $21.12 + $0.00 |
| 2026-10-23 | SC | SC20260034 | Highway | CEMENT MASON/CONCRETE FINISHER (BERKELEY, DORCHESTER) | $14.79 + $0.00 | $21.86 + $0.00 |
| 2026-10-23 | SC | SC20260034 | Highway | CEMENT MASON/CONCRETE FINISHER (CHARLESTON) | $14.33 + $0.00 | $21.18 + $0.00 |
| 2026-10-23 | SC | SC20260035 | Highway | CARPENTER, FORM WORK ONLY (FAIRFIELD, KERSHAW, RICHLAND, SAL | $15.04 + $0.00 | $22.23 + $0.00 |
| 2026-10-23 | SC | SC20260035 | Highway | CARPENTER, FORM WORK ONLY (LEXINGTON) | $14.50 + $0.00 | $21.44 + $0.00 |
| 2026-10-23 | SC | SC20260035 | Highway | CEMENT MASON/CONCRETE FINISHER | $13.65 + $0.00 | $20.18 + $0.00 |
| 2026-10-23 | SC | SC20260035 | Highway | IRONWORKER, REINFORCING | $15.02 + $0.00 | $22.20 + $0.00 |
| 2026-10-23 | SC | SC20260035 | Highway | LABORER, TRAFFIC CONTROL-CONE SETTER (CALHOUN, FAIRFIELD, KE | $10.87 + $0.00 | $16.07 + $0.00 |
| 2026-10-23 | SC | SC20260036 | Highway | CEMENT MASON/CONCRETE FINISHER | $13.16 + $0.00 | $19.45 + $0.00 |
| 2026-10-23 | SC | SC20260036 | Highway | IRONWORKER, REINFORCING | $15.02 + $0.00 | $22.20 + $0.00 |
| 2026-10-23 | SC | SC20260036 | Highway | LABORER: MASON TENDER-CEMENT/CONCRETE | $10.40 + $0.00 | $15.37 + $0.00 |
| 2026-10-23 | SC | SC20260036 | Highway | LABORER: PIPELAYER | $14.46 + $0.00 | $21.38 + $0.00 |
| 2026-10-23 | SC | SC20260036 | Highway | POWER EQUIPMENT OPERATOR: BULLDOZER | $17.38 + $0.00 | $25.69 + $0.00 |
| 2026-10-23 | SC | SC20260037 | Highway | CEMENT MASON/CONCRETE FINISHER | $12.64 + $0.00 | $18.69 + $0.00 |
| 2026-10-23 | SC | SC20260037 | Highway | IRONWORKER, REINFORCING | $15.02 + $0.00 | $22.20 + $0.00 |
| 2026-10-23 | SC | SC20260037 | Highway | LABORER, ASPHALT INCLUDES ASPHALT DISTRIBUTOR, SHOVELER, AND | $11.54 + $0.00 | $17.06 + $0.00 |
| 2026-10-23 | SC | SC20260037 | Highway | LABORER, ASPHALT INCLUDES ASPHALT DISTRIBUTOR, SHOVELER, AND | $11.62 + $0.00 | $17.18 + $0.00 |
| 2026-10-23 | SC | SC20260037 | Highway | LABORER, TRAFFIC CONTROL-FLAGGER (ANDERSON, SPARTANBURG, YOR | $10.13 + $0.00 | $14.98 + $0.00 |
| 2026-10-23 | SC | SC20260038 | Highway | CEMENT MASON/CONCRETE FINISHER | $13.16 + $0.00 | $19.45 + $0.00 |
| 2026-10-23 | SC | SC20260038 | Highway | IRONWORKER, REINFORCING | $15.02 + $0.00 | $22.20 + $0.00 |
| 2026-10-23 | SC | SC20260039 | Highway | CEMENT MASON/CONCRETE FINISHER (ABBEVILLE, CHEROKEE, CHESTER | $11.63 + $0.00 | $17.19 + $0.00 |
| 2026-10-23 | SC | SC20260039 | Highway | CEMENT MASON/CONCRETE FINISHER (CHESTERFIELD, CLARENDON, DIL | $13.02 + $0.00 | $19.25 + $0.00 |
| 2026-10-23 | SC | SC20260039 | Highway | IRONWORKER, REINFORCING | $15.64 + $0.00 | $23.12 + $0.00 |
| 2026-10-23 | SC | SC20260039 | Highway | LABORER, TRAFFIC CONTROL-FLAGGER (ABBEVILLE, CHEROKEE, CHEST | $10.15 + $0.00 | $15.00 + $0.00 |
| 2026-10-23 | SC | SC20260039 | Highway | LABORER, TRAFFIC CONTROL-FLAGGER (LANCASTER) | $10.83 + $0.00 | $16.01 + $0.00 |
| 2026-10-23 | SC | SC20260040 | Highway | CEMENT MASON/CONCRETE FINISHER | $14.11 + $0.00 | $20.86 + $0.00 |
| 2026-10-23 | SC | SC20260040 | Highway | IRONWORKER, REINFORCING | $15.64 + $0.00 | $23.12 + $0.00 |
| 2026-10-23 | SC | SC20260040 | Highway | LABORER (COLLETON) | $10.16 + $0.00 | $15.02 + $0.00 |
| 2026-10-23 | SC | SC20260040 | Highway | LABORER, TRAFFIC CONTROL-CONE SETTER (ALLENDALE, BAMBER, BAR | $12.98 + $0.00 | $19.19 + $0.00 |
| 2026-10-23 | SC | SC20260040 | Highway | LABORER, TRAFFIC CONTROL-CONE SETTER (BEAUFORT, COLLETON, GE | $12.84 + $0.00 | $18.98 + $0.00 |
| 2026-10-09 | AK | AK20260001 | Building | LABORER: GROUP 1 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $40.25 + $34.26 | $42.25 + $35.01 |
| 2026-10-09 | AK | AK20260001 | Building | LABORER: GROUP 2 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $41.25 + $34.26 | $43.25 + $35.01 |
| 2026-10-09 | AK | AK20260001 | Building | LABORER: GROUP 3 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $42.15 + $34.26 | $44.15 + $35.01 |
| 2026-10-09 | AK | AK20260001 | Building | LABORER: GROUP 3A (SOUTH OF THE 63RD PARALLEL & WEST OF | $46.53 + $34.26 | $48.68 + $35.01 |
| 2026-10-09 | AK | AK20260001 | Building | LABORER: GROUP 3B (SOUTH OF THE 63RD PARALLEL & WEST OF | $54.01 + $28.81 | $57.71 + $29.06 |
| 2026-10-09 | AK | AK20260005 | Residential | LABORER: GROUP 1 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $40.25 + $34.26 | $42.25 + $35.01 |
| 2026-10-09 | AK | AK20260005 | Residential | LABORER: GROUP 2 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $41.25 + $34.26 | $43.25 + $35.01 |
| 2026-10-09 | AK | AK20260005 | Residential | LABORER: GROUP 3 (SOUTH OF THE 63RD PARALLEL & WEST OF L | $42.15 + $34.26 | $44.15 + $35.01 |
| 2026-10-09 | AK | AK20260005 | Residential | LABORER: GROUP 3A (SOUTH OF THE 63RD PARALLEL & WEST OF | $46.53 + $34.26 | $48.68 + $35.01 |
| 2026-10-09 | AK | AK20260005 | Residential | LABORER: GROUP 3B (SOUTH OF THE 63RD PARALLEL & WEST OF | $54.01 + $28.81 | $57.71 + $29.06 |
| 2026-10-09 | MT | MT20260059 | Building | ELECTRICIAN: LOW VOLTAGE WIRING FOR ALARMS AND COMPUTERS (ME | $23.90 + $160.74 | $23.90 + $11.51 |
| 2026-10-09 | ND | ND20260001 | Highway | CARPENTER | $38.70 + $9.00 | $39.45 + $9.75 |
| 2026-10-09 | ND | ND20260001 | Highway | CEMENT MASON/CONCRETE FINISHER | $38.70 + $9.00 | $39.45 + $9.75 |
| 2026-10-09 | NJ | NJ20260007 | Residential | CARPENTER (INCLUDES DRYWALL HANGING) | $48.27 + $5.79 | $48.27 + $11.38 |
| 2026-10-09 | NJ | NJ20260007 | Residential | IRONWORKER: REINFORCING | $53.24 + $0.40 | $53.24 + $40.40 |
| 2026-10-09 | NJ | NJ20260007 | Residential | IRONWORKER: STRUCTURAL | $54.24 + $0.40 | $54.24 + $40.40 |
| 2026-10-09 | PA | PA20260003 | Building | CARPENTER/LATHER | $55.82 + $30.09 | $57.72 + $30.39 |
| 2026-10-09 | PA | PA20260003 | Building | MILLWRIGHT | $54.54 + $38.78 | $55.54 + $40.47 |
| 2026-10-09 | PA | PA20260003 | Building | ELECTRICIAN | $70.97 + $46.13 | $75.05 + $47.02 |
| 2026-10-09 | PA | PA20260003 | Building | ELECTRICIAN (SOUND AND COMMUNICATION TECHNICIAN) (INSTALLATI | $63.97 + $30.40 | $69.62 + $38.39 |
| 2026-10-09 | PA | PA20260003 | Building | PLUMBER | $70.53 + $38.81 | $73.73 + $39.86 |
| 2026-10-09 | PA | PA20260004 | Heavy | ELECTRICIAN (BUCKS COUNTY: STARTING AT THE DELAWARE RIVER AN | $70.97 + $46.13 | $75.05 + $47.02 |
| 2026-10-09 | PA | PA20260078 | Building | ELECTRICIAN (INCLUDING ALARM INSTALLATION, INSTALLATION OF S | $58.63 + $46.58 | $62.41 + $47.77 |
| 2026-10-09 | PA | PA20260083 | Building | MILLWRIGHT | $54.54 + $38.78 | $55.54 + $40.47 |
| 2026-10-09 | PA | PA20260083 | Building | ELECTRICIAN (INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS | $46.89 + $35.85 | $69.62 + $38.39 |
| 2026-10-09 | PA | PA20260083 | Building | ELECTRICIAN (INCLUDES SOLAR PANEL WIRING AND INSTALLATION; E | $58.63 + $46.58 | $62.41 + $47.77 |
| 2026-10-09 | PA | PA20260083 | Building | PLUMBER | $70.53 + $38.81 | $73.73 + $39.86 |
| 2026-10-09 | PA | PA20260087 | Building | MILLWRIGHT | $54.54 + $38.78 | $55.54 + $40.47 |
| 2026-10-09 | PA | PA20260087 | Building | ELECTRICIAN (ALARM INSTALLATION ONLY) | $58.63 + $46.58 | $62.41 + $47.77 |
| 2026-10-09 | PA | PA20260087 | Building | PLUMBER | $70.53 + $38.81 | $73.73 + $39.86 |
| 2026-10-09 | PA | PA20260099 | Building | MILLWRIGHT | $54.54 + $38.78 | $55.54 + $40.47 |
| 2026-10-09 | PA | PA20260099 | Building | ELECTRICIAN (INCLUDES ALARM INSTALLATION, SOLAR PANEL WIRING | $58.63 + $46.58 | $62.41 + $47.77 |
| 2026-10-09 | PA | PA20260099 | Building | PLUMBER | $70.53 + $38.81 | $73.73 + $39.86 |
| 2026-10-09 | PA | PA20260114 | Residential | ELECTRICIAN | $70.97 + $46.13 | $75.05 + $47.02 |
| 2026-10-09 | PA | PA20260114 | Residential | ELECTRICIAN (SOUND AND COMMUNICATION TECHNICIAN) | $62.72 + $34.50 | $69.62 + $38.39 |
| 2026-10-09 | RI | RI20260001 | Building | LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 5: Toxic was | $33.05 + $24.05 | $37.50 + $24.85 |
| 2026-10-02 | MD | MD20260034 | Heavy | POWER EQUIPMENT OPERATOR - DRILL - RIG | $32.00 + $120.85 | $32.00 + $12.85 |